Project for the first European galvanising plant in Belgium
Challenge
Complete all work in record time, as the machine can only be shut down for a maximum of 36 hours. This included completely dismantling the existing rail, reassembling it, aligning it perfectly and repointing it.
Proposal
We proposed the use of Chockfast® Red because it ensures perfect alignment and adequate resistance to possible oil and grease leaks from the coil feeder.
Implementation
Finres was involved in the entire process of this project. It helped to determine the work procedure, schedule and coordination with the mechanical team. Effective collaboration for optimal and timely results.
"Following a request from SEGAL to repair the seat of a rail coil lift truck (30-tonne capacity), we agreed with Mr Scheppers on an action plan to meet the specifications. After SEGAL's purchasing process, FINRES was ready to begin the necessary actions according to the production schedule. On the day, the FINRES and SEGAL teams worked together to meet the deadlines set by SEGAL. Following this joint intervention, we were able to test the operation of the loading trolley and conclude that the work carried out was satisfactory. If I am consulted for similar work in the future, I will be happy to recommend FINRES for its competence, professionalism and availability.
GEORGES PHILIPPET
Maintenance Manager - SEGAL

Other news

Chockfast Orange - Rail grouting
When injection is the last option left

Grouting of a compressor with Chockfast® epoxy grout
Pouring Chockfast® Red into anchor pockets and between the concrete slab and the compressor skid to ensure alignment and vibration control.

Securing the largest European pivoting bridge
Injection of Chockfast® Orange between the bridge walkway deck and the bridge support carousel to support the weight of the bridge and protect its system.