Grouting of a compressor with Chockfast® epoxy grout

Challenge

TGE was looking for a flexible and experienced partner to grout three Burchkart compressors as part of the large liquefied gas silo project at the Antwerp gas terminal, now known as Advario. The challenge was to ensure safe grouting procedures while working outdoors in winter conditions without direct access to the injection area.

Proposal

Grouting of the pockets and skids was proposed using Chockfast Red, and filling of the skids was proposed using BASF 145 PG.

Implementation

While complying with API standards for casting, Finres found innovative solutions to ensure the correct resin application temperatures. This made it possible to meet a tight casting schedule in difficult weather conditions.

"In order to grout three compressor skids, weighing approximately 34,000 kg each, with epoxy grout and also fill the frame with cement grout, we were looking for a flexible partner who was ready to take on this challenge, which included lifting the three compressors to allow the concrete surface to be prepared. Finres managed to complete the work on time, quickly and smoothly. As great attention was paid to determining the correct approach and preparing the work, we are extremely satisfied with the cooperation with Finres and the final result for this complex mission."
LUIS PEREIRA
Site QA/QC Engineer - TGE GAS ENGINEERING GMBH